Construction
Update - Sept 2006
The main
building foundation construction is entering its last
stage. To date, building piles for Block 1 and 8 have
been completed whilst works for Block 2 and 7 will be
completed very soon. As for the whole basement car
parking area, 82% of the piles have also been completed.
The tests – meticulously conducted by our team which
includes specialists from United Kingdom and Singapore –
had been able to verify the design capacity of the
foundation piles. These experts verified the detailed
test reports and necessary design modifications were
made where necessary to achieve the design objectives
|