Construction Update - May 2006

The construction of the sales and site office is progressing as scheduled. To date, all the structural concrete works have been completed. The special T girders for support of the roof have been installed and interior works have been substantially completed in May ‘06.

The new sales office is operational from 20th May ‘06. The main building foundation construction is currently in progress. The international tenders for the main building superstructure construction have already been called and are currently being evaluated. Only international contractors
are being considered for the superstructure construction.

 

Installation of Strain Gauges for the 1200mm Diameter Test Piles