Construction Update - Feb 2007

1. Piling Work 100% completed
2. Pile Tests100% completed
3. The Main Contractor, Guang Dong Overseas Construction Group Ltd has started mobilization works including:
        a. Hiring of local/ Chinese personnel
        b. Joint survey with IVCC
        c. Submission of dewatering methodology
        d. Construction of Site office for client/ consultant
 

PROJECT OFFICE, STRUCTURE COMPLETED